An instalment plan should allocate buyer payments to clearly defined contractual events, not just dates on a marketing graphic. Construction is measurable, but evidence has to be independent enough for the buyer and lender to rely on it. This guide shows a buyer how to connect payment milestones with legal safeguards, technical inspections and documentary records.

Start with the legal basis, not the payment calendar
Before the first meaningful transfer, your independently instructed advocate should check the seller’s legal authority, site tenure, encumbrances, approved development documents and the transaction’s escrow or stakeholder terms. A developer receiving money does not by itself prove that a building is authorised or that the buyer will obtain a registrable unit.
Under Kenya’s NCA framework, project registration and competent contractors and consultants are important checks. The NCA project-registration guidance explains the documentary framework. County development permissions, environmental approvals where applicable and utility arrangements require their own checks: NCA registration does not replace them.
A stage-gate checklist
Parties should agree in writing what “foundation complete”, “structure complete”, “roofing”, “first fix”, “finishes” and “practical completion” mean. An engineer’s dated report, signed site diary, photograph log and independent inspection can be stronger than marketing drone footage. The contract should identify who certifies each milestone and what happens if the work falls short.
Construction stage verification can be integrated into payment administration. Some contracts are time-based rather than progress-based; those create a different cash-flow risk for a buyer and need a clear contingency and dispute process.
| Payment stage | Evidence to request | Common risk |
|---|---|---|
| Deposit | Executed agreement, ownership and approvals review | Funds paid before legal protection is clear |
| Structural milestones | Engineer or qualified inspector certificate plus dated photos | Progress asserted but not independently certified |
| Finishes | Specification checklist, sample comparison and defect log | Substituted materials without documented consent |
| Handover | Practical-completion documents, service tests and keys | Final payment before utilities or core systems work |
What a credible progress report contains
A strong report states the date, exact block, floor and work package; the planned versus achieved work; the independent person or contractor responsible; visible defects; critical dependencies; and the next verification date. It should distinguish permanent construction from temporary site works. Photographs must have captions that identify the structure and orientation, not just visually appealing angles.
Check whether payment is tied to the advertised project’s progress or to the specific unit and associated common facilities. A nearly finished unit can still be unusable if the lift, water system, fire exits or permanent electricity are not ready.
Escalation when evidence is missing
Do not rely solely on a sales representative’s statement that delays are “normal”. Document the requested evidence, contractual reference, deadline and remedy. Ask your advocate whether the conditions for payment have actually arisen, whether there is a lawful withholding right, and whether notice requirements apply. Withholding instalments without legal advice can itself create contractual risk.
For buyers abroad, an independent surveyor’s inspection is often more valuable than an extra set of promotional photographs. Read the Vellora progress tracker and the Gazebo Apartments progress tracker as examples of project-specific evidence questions.
Related reading and next steps
Continue with Nommadj’s existing reporting on the off-plan due-diligence checklist and Vellora document checks. These resources add context; verify property-specific documents and price quotations independently.
Frequently asked questions
Is a developer’s photo sufficient to approve an instalment?
Not necessarily. Seek the contractual milestone definition and independent technical evidence where the amount is material.
Does NCA registration prove an apartment is ready to occupy?
No. It is one of several statutory and technical checks; occupation and handover require additional evidence.
What if a payment deadline arrives before the work does?
Have an advocate interpret the contract and send any required formal notices rather than assuming either party’s position is automatic.
Sources, methodology and disclosure
This guide was prepared for Nommadj on 23 November 2026 using the sources below and the site’s existing editorial archive. Any worked calculations are illustrative; they are not an offer, an official property valuation, or a forecast. Legal and tax outcomes depend on the circumstances of an individual transaction.